0142 Project Meetings Periodic weekly, monthly and quarterly reports shall be submitted by the Contractor indicating the progress of works.
The monthly progress shall indicate: -
The activities carried out in the month and the total to date including value of work.
Problems encountered, affected portions of work and their effect on sequential activities.
The Quarterly report shall indicate:-
The activities carried out in the quarter and the total to date including value of work.
The comparative effect of the activities to the proposed schedule.
The problems encountered and their effect on the succeeding work and over all completion time.
The validity of the float proposed in the schedule.