BaTCoDA

0143 Project Meetings
Project meetings involving the Investor, Engineer and Contractor shall be held at suitable locations, preferably at the location of work at agreed dates but no less than once a month to review the progress of work. The minutes of such meeting shall be duly recorded.
0144 Photographs
Photographs on progress records shall be taken by the Contractor at instructed frequencies but no less than required to indicate critical work stages and progress. A minimum of one print of each shall be displayed at site and two copies submitted to the Engineer.
Full set of completed work photographs shall be submitted by the Contractor at the end of the work. The cost of all such photographs shall be borne by the contractor.


Yüklə 475,5 Kb.

Dostları ilə paylaş:
1   ...   11   12   13   14   15   16   17   18   ...   249




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin