01312 ENGINEER'S APPROVAL

The phrases in the Technical Specification "approval, Engineer’s approval, etc" shall be understood as obtaining the prior approval of the engineer and his representative in compliance with the powers of the Engineer as provided for in the Conditions of Contract.


014 PROJECT RECORDS
0141 Construction Schedule
01411 General

Adequate work plan, indicating delivery of materials and execution of the works within the time frame given for completion requires the preparation of work schedule as described hereunder. The Contractor shall use this same schedule to monitor the progress of the works and evaluate the performance. The Construction schedule once approved shall form an integral part of the Contract.



01412 Timing

Unless other wise instructed, the timing used in the schedule shall always refer to Calendar days, weeks or months.




Yüklə 475,5 Kb.

Dostları ilə paylaş:
1   ...   7   8   9   10   11   12   13   14   ...   249




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©muhaz.org 2024
rəhbərliyinə müraciət

gir | qeydiyyatdan keç
    Ana səhifə


yükləyin